US Power Grid Projects Map
20 of the biggest US transmission projects, from HVDC links to new 765 kV backbones, and 5 of the largest new power plants, with status, size, cost and in-service date for each.
Open the mapHiring power engineers?The US grid is in its biggest build-out in decades. This map tracks 20 of the largest transmission projects across 26 states, from long-distance HVDC lines that move wind and hydropower hundreds of miles to the new 765 kV backbones planned in Texas, the Midwest and Virginia, plus 5 of the biggest new power plants built or planned to feed data centers and industry. Every project links to the developer, regulator or news report its figures come from.
Filter by type of project or status, or search for a developer or state. Click any line or plant for its size, cost and expected in-service date.
Map of 25 major US power grid projects
20 of the largest high-voltage transmission projects and 5 of the largest new power plants, across 26 states. Solid lines are in service; dashed lines are being built, approved or still in permitting. Click a line or plant for the developer, size, status, expected in-service date and source. Updated November 2026.
Lines are drawn straight between the end points (and main stops) the developer has named, to show which regions a line will join. They are not the surveyed route, which for many lines is still being decided.
Every project on the map
| Project | Developer | Type | States | Size | Status | Cost | In service | Source |
|---|---|---|---|---|---|---|---|---|
| SunZia Wind Largest wind farm in the US | Pattern Energy | Large new power plants | NM | 3,500 MW | In service | – | 2026 | Jun 12, 2026 |
| SunZia Transmission Carries power from the SunZia wind farm in New Mexico to Arizona and California | Pattern Energy | Long-distance HVDC lines | NM, AZ | 550 mi, 525 kV HVDC, 3,000 MW | In service | – | 2026 | Jun 2026 |
| Champlain Hudson Power Express Canadian hydropower to New York City (Astoria, Queens) | Transmission Developers and Hydro-Quebec | Long-distance HVDC lines | NY | 339 mi, HVDC, underwater and underground, 1,250 MW | In service | $6B | May 2026 | May 13, 2026 |
| New England Clean Energy Connect Quebec border to Lewiston, Maine | Avangrid | Long-distance HVDC lines | ME | 145 mi, HVDC, 1,200 MW | In service | – | Jan 2026 | Jan 16, 2026 |
| Homer City Energy Campus Gas plant with seven GE Vernova turbines for a data center campus | Homer City Generation (built by Kiewit) | Large new power plants | PA | 4,500 MW | Under construction | – | 2027 | Jun 2, 2026 |
| Greenlink West Las Vegas to Fort Churchill near Yerington | NV Energy | 765 kV and 500 kV AC lines | NV | 472 mi, 525 kV, 4,000 MW | Under construction | $4.2B | May 2027 | Sep 2024 |
| TransWest Express Wyoming wind to Utah, Nevada and California | TransWest Express LLC (Anschutz) | Long-distance HVDC lines | WY, CO, UT, NV | 732 mi, AC and HVDC, 3,000 MW | Under construction | – | 2030 (first stage) | Jan 2026 |
| Entergy Louisiana gas plants for Meta Hyperion (first three) Gas combined cycle: two in Richland Parish, one in St. Charles Parish | Entergy Louisiana | Large new power plants | LA | 2,300 MW | Under construction | – | – | Nov 18, 2026 |
| Orange County Advanced Power Station Gas combined cycle near Bridge City; more than 80% complete | Entergy Texas | Large new power plants | TX | 1,200 MW | Under construction | – | – | Nov 18, 2026 |
| Boardman to Hemingway Boardman, Oregon to Melba, Idaho | Idaho Power and PacifiCorp | 765 kV and 500 kV AC lines | OR, ID | 290 mi, 500 kV, 1,000 MW | Under construction | – | 2027 | Nov 18, 2026 |
| Grain Belt Express Phase 1 (Kansas to Missouri) is first to be built | Invenergy | Long-distance HVDC lines | KS, MO, IL, IN | 800 mi, 600 kV HVDC, 5,000 MW | Approved, not yet built | $11B | 2030 | Nov 2026 |
| Permian 765 kV line: Glen Rose to Reeves County Approved by Texas regulators Aug 28, 2026; part of the Permian Basin Reliability Plan | Oncor | 765 kV and 500 kV AC lines | TX | 400 mi, 765 kV | Approved, not yet built | – | – | Sep 2, 2026 |
| Permian 765 kV line: San Antonio area to the Permian Approved by Texas regulators Aug 28, 2026 | Texas transmission utilities | 765 kV and 500 kV AC lines | TX | 765 kV | Approved, not yet built | – | – | Aug 28, 2026 |
| Phantom to Crossroads to Potter 765 kV First 765 kV line in the Southwest Power Pool | Xcel Energy | 765 kV and 500 kV AC lines | TX, NM | 765 kV | Approved, not yet built | – | – | Feb 2025 |
| Big Stone South to Brookings to Lakefield Junction 765 kV Part of the MISO Tranche 2.1 765 kV backbone | MISO Tranche 2.1 | 765 kV and 500 kV AC lines | SD, MN | 765 kV | Approved, not yet built | – | – | Nov 18, 2026 |
| East Adair to Minnesota/Iowa State Line 765 kV (EASL) Central Iowa north to the Minnesota line, joining the Lakefield Junction path | Ameren Transmission (ATXI), GridLiance Heartland and Dairyland Power | 765 kV and 500 kV AC lines | IA, MN | 187 mi, 765 kV | Approved, not yet built | – | June 2034 | Nov 18, 2026 |
| Woodford County to Illinois-Indiana State Line 765 kV (WIIL) Two new 765 kV lines and a new substation | Ameren Transmission (ATXI), GridLiance Heartland, Dairyland Power and IMEA | 765 kV and 500 kV AC lines | IL, IN | 88 mi, 765 kV | Approved, not yet built | $718M | 2034 | Nov 18, 2026 |
| Entergy Louisiana seven more gas plants for Meta Hyperion Richland and Pointe Coupee parishes; needs Louisiana PSC approval | Entergy Louisiana | Large new power plants | LA | 5,200 MW | Planning and permitting | $12.9B | – | Aug 7, 2026 |
| SOO Green HVDC Link Iowa to the Chicago area | SOO Green Renewable Rail | Long-distance HVDC lines | IA, IL | 350 mi, HVDC, mostly underground along rail lines | Planning and permitting | – | – | Sep 15, 2026 |
| North Plains Connector Montana to North Dakota; federal environmental review done Aug 2026 | Grid United and ALLETE | Long-distance HVDC lines | MT, ND | HVDC | Planning and permitting | – | – | Sep 15, 2026 |
| Southern Spirit Would link the Texas (ERCOT) grid with the Southeast | Pattern Energy | Long-distance HVDC lines | TX, LA, MS | HVDC | Planning and permitting | – | – | Sep 15, 2026 |
| Greenlink North Ely to Yerington | NV Energy | 765 kV and 500 kV AC lines | NV | 235 mi, 525 kV | Planning and permitting | – | Dec 2028 | May 7, 2025 |
| ERCOT 765 kV Eastern Backbone Endorsed by ERCOT stakeholders; still needs Texas PUC approval | AEP, CenterPoint Energy, CPS Energy and Oncor | 765 kV and 500 kV AC lines | TX | 1,109 mi, 765 kV | Planning and permitting | $9.4B | – | Mar 5, 2026 |
| Valley Link: Valley North 765 kV Putnam County, West Virginia to Frederick County, Maryland | Valley Link (Dominion, FirstEnergy, Transource) | 765 kV and 500 kV AC lines | WV, MD | 260 mi, 765 kV | Planning and permitting | – | – | Feb 27, 2025 |
| Valley Link: Joshua Falls to Yeat 765 kV Campbell County to northern Virginia; route revised in 2026 | Valley Link (Dominion, FirstEnergy, Transource) | 765 kV and 500 kV AC lines | VA | 155 mi, 765 kV | Planning and permitting | – | – | Jul 17, 2026 |
Cost is the developer's or regulator's published estimate; – means no figure has been published. In-service dates are the developer's latest target and often move.
What the grid build-out means for hiring
The projects on this map add 6,112 miles of new high-voltage line, most of it 765 kV or HVDC, a scale the US has not built in a generation. Each one needs transmission line and substation design engineers, protection and controls engineers, power system planners, civil and structural engineers for towers and foundations, and project and construction engineers in the field. Many of these engineers are already in short supply, and data center demand is pulling on the same talent.
Texas stands out: the 765 kV lines approved for the Permian Basin and the planned Eastern Backbone will run through the Dallas-Fort Worth, Houston and San Antonio regions. Apollo Technical recruits electrical engineers and renewable energy engineers for utilities, developers and the firms that design and build these projects, with local teams in Houston, Austin and across Texas. For what these roles pay, try the engineering salary calculator.
Related trackers: the US data center map, the Data Center Workforce Report, the new factory construction map and the semiconductor plants map, all large new loads that these lines and plants are being built to serve.
How this map is built
The map covers major new transmission lines (long-distance HVDC and 765 kV or 500 kV AC) and the largest new power plants, checked against developer announcements, grid operator and regulator records and news reports in November 2026. Nuclear projects are not included. Lines are drawn straight between the end points the developer has named, to show which regions they join; most surveyed routes are still being decided. Cost and in-service dates are the developer’s or regulator’s latest published figures and change often. Know a major project we should add? Email info@apollotechnical.com.
Power grid projects FAQ
What is a 765 kV transmission line?
765 kilovolts is the highest voltage used on the US grid. One 765 kV line can carry about as much power as six 345 kV lines, with lower losses and a narrower total footprint, which is why Texas, the Southwest Power Pool, MISO and PJM are all planning 765 kV backbones. Texas approved its first 765 kV lines in 2025 and 2026.
What is an HVDC transmission line?
High-voltage direct current lines move large amounts of power over long distances with lower losses than AC lines, and link grids that are not synchronized. Converter stations at each end turn AC into DC and back. SunZia, the Champlain Hudson Power Express and the New England Clean Energy Connect all entered service in 2026.
What is the biggest transmission line being built in the US?
By capacity, Invenergy’s Grain Belt Express, an 800-mile, 5,000 MW HVDC line from Kansas to the Illinois-Indiana border, is the largest approved project, with its first phase starting construction. The largest line under construction is TransWest Express, 732 miles from Wyoming to Nevada.
What engineers do transmission and power plant projects need?
Transmission line and substation design engineers, protection and controls engineers, power system planning and interconnection engineers, civil, structural and geotechnical engineers, and project and construction engineers. Power plants add mechanical, electrical and instrumentation and controls engineers for commissioning and operations.
How often is the map updated?
Monthly. New approvals, construction starts, in-service dates and cancellations are added as they are reported, each with its source. This edition was checked in November 2026.